Scandlines Catering ApS – MF PRINSESSE BENEDIKTE

About

Business: Maritme Market
Client: Scandlines Catering Aps
Delivered Date: 10.2017
Project Scope: surface protection and outfitting works in the “turn-key” system in the public toilets

PENTA finished works on MF Princesse Benedikte for Scandlines Danmark Aps on 20 October,2017. This is subsequent Ferry was completed for the Client within scope. Ship of the overall length 142m, passenger capacity 1140 and car capacity 364. PENTA scope of work included surface protection and outfitting works in the „turn-key” system in the public toilets. Scope of work was similar as on Prins Richard.

Main scope of works was done in the Puttgarden shipyard in Germany.

The implementation was a huge challenge due to short duration of the project (three weeks) and very strict health and safety requirements due to the work completed during the ship’s operation on line Puttgarden – Rødby.

The Prinsesse Benedikte ferry refit project represents a successful realization in the short period of time.